Oniro Platform v2.0 Release checklist
Rationale
This is the main checklist to release Oniro v2.0. It is based on the EF Project Handbook, Release section.
High level checklist
IP review and formal approval by EF checklist:
-
Create a Release in the PMI. - Only the people with specific rights can do this.
-
Provide a Release plan, fill in the fields related with the new release in the PMI. -
Generate and review an IP Log, or ask the IP Team to review the code. -
Send an email to the EMO to start the community review. - The community review usually lasts at least 2 weeks to give time to people to check it out.
-
Get PMC approval. -
Wait for the end of release review and the official release - The review happens every 1st and 3rd Wednesday of the month.
Content
Documentation
Technical documentation:
-
Release notes -
Download, build, install (consume) documentation.
Product documentation:
-
Epics update -
Oniro Platform Release Roadmap document
Communication checklist
These are the activities that will be performed related with communication and marketing
-
Key messages -
Entry on our wiki -
Text and links on website -
Media kit -
Social media campaign
Additional activities
Other activities related with the release that needs to be performed, related with IT, Member companies, product management, documentation, etc.
-
Timeline definition -
Coordination structure and sync points